CPUC Extends BioMAT Program, Adopts Important Changes

The CPUC voted 5-0 to extend the BioMAT program and make several critical changes to the program.  The CPUC’s Decision extends the program end date to the end of 2025.  This is critical since the utilities have only procured about 20 percent of the 250 megawatts required by the program.  The CPUC Decision also increases delivery flexibility for project developers, establishes deadlines for utilities to review project eligibility and approve contracts, and establishes a non-bypassable charge so that all rate-payers will share the costs of the program.  The CPUC proposed the non-bypassable charge in recognition of the fact that BioMAT projects provide important statewide benefits that all ratepayers should help to pay for, not just the purchasing utility’s customers.

See CPUC’s Proposed Decision on BioMAT (July 24, 2020), which was adopted by the Commission on August 28.